April 2025 Construction Photos

Click on the images below to view full screen.

As part of the 167th Street interchange reconstruction, south-facing ramps will be added to the existing northbound ramps to provide access to U.S. 69 from both directions.

Crew members install a box culvert under U.S. 69 at 167th Street.

A truck pumps concrete for the bridge deck pour on the new U.S. 69 southbound bridge over 119th Street.

Heavy equipment is used to drive piling for a new bridge foundation near Indian Creek.

Sodding work begins in the medians along 119th Street.

Workers drill shafts to support the new northbound U.S. 69 bridge over 167th Street.

Crews finish work under the new U.S. 69 bridges over College Blvd.

Grading and dirt work set the stage for future paving between northbound and southbound U.S. 69 and I‑435.

Contractor staging areas, like the ones at U.S. 69/135th Street, support U.S. 69 expansion work.

During night work, construction workers lay pavement for a reconstructed ramp to 135th Street.

Crews install rebar to prepare for the deck pour on northbound U.S. 69 bridge over 119th Street.

In April, crews began installing structures that will support toll collection equipment for the U.S. 69 express lanes.

A tolling gantry is put in place across newly built U.S. 69 northbound lanes.